Post-Brexit lorry park scrapped after JR threatened

The proposed lorry park at Stanford, near Folkestone, was designed to alleviate the impact of ‘Operation Stack’, which is the process by which lorries are parked on the M20 motorway in Kent if there is disruption to cross-Channel traffic.

But transport secretary Chris Grayling this week announced that the government was withdrawing the plans for the lorry park.

He said it had not been possible to defend a judicial review which had been lodged against the plan by local campaigners on the grounds that the government had not carried out an environmental impact assessment of the scheme. The campaigners also claimed that the project should have been subject to a development consent order (DCO).

Government agency Highways England was to develop the facility using powers available under Section 115 of the Highways Act 1980, replacing the need for a planning application.

Grayling said the government would now start to look at alternative solutions.

“We are immediately starting the process to promote a lorry park through the normal planning process, including a full environmental impact assessment, as a potential permanent solution to Operation Stack,” he said.

“As part of this we will reassess the scope, scale and location of our solutions, taking into account changes since the original concept of the lorry park was promoted.”

Highways England has been tasked with looking at alternative solutions, including a new assessment of the options for holding large numbers of lorries at a site near the M20, and an interim solution that would hold freight traffic on the motorway while keeping it open in both directions for other vehicles.

The government agency said a decision on the interim option being taken forward would be announced in early 2018, with delivery complete by March 2019.

“Improvements at the port, and changes we have made to traffic management on the A20 near Dover, have delivered real improvements and have also helped prevent Operation Stack from being implemented,” said Highways England project director John Kerner.

“Along with our partners we are better prepared than ever, but a better plan for dealing with more widespread disruption is still needed.”

Article originally appeared on Planning Resource

The Institute cannot confirm the accuracy of this story or confirm that it presents a balanced view. If you feel this is inaccurate we would welcome your perspective and evidence that this is the case.

Shopping Basket
Scroll to Top

Your membership questions answered

View our frequently asked questions or contact our dedicated account manager for further support.

You can reset your password here. If you’re still having issues, please send us a message below.

We have many ways you can pay for your membership.

  • Credit card
  • Online
  • Invoice
  • PO

You can renew/upgrade your membership here.

To find out more, send us a message below.

You will receive a reminder email from our dedicated membership account manager 4 weeks before your renewal date. This email will contain all the information you need to renew.

You can also renew your membership online here.

You can update your contact details here. Alternatively, please send a message to our membership account manager below.

Please send a message to our membership account manager below. 

Still need support?

Our dedicated Membership Account Manager is on
hand to assist with any questions you might have.

Request a callback

Leave a message and our team will call you back

"*" indicates required fields

Name*

Send us a message

We’ll be in touch with you soon.

Name(Required)
Email(Required)